Propuesta de mejora al plan de manejo ambiental del humedal jaboque, mediante la evaluación de impacto ambiental caso de estudios barrio unir II en el tercio medio del humedal, bogotá D.C.

View/ Open
Date
2016-01-27Author
Gómez Niño, María Camila
Triana Rincón, Elizabeth
xmlui.dri2xhtml.METS-1.0.item-advisor
Mariño Ramos, Angélica / Director
Metadata
Show full item recordAbstract
El humedal Jaboque se encuentra localizado en la ciudad de Bogotá localidad decima de Engativá. Recientemente se realizó la aprobación del Plan de Manejo Ambiental del humedal (PMA) con el fin de conservar el ecosistema y mejorar las condiciones de este. El PMA fue elaborado con estudios realizados entre los años 1998 y 2006 por la organización ADESSA contratada por la EAAB, siendo ese último el año de entrega del documento.
Si bien el PMA fue aprobado hasta el 2015, el documento no presentó mayores cambios en comparación con la versión de 2006, razón por la cual las características, aciertos y desaciertos de ese entonces permanecieron en el texto actualmente aprobado. Con base en el PMA se dio comienzo al presente trabajo, en donde se realiza una investigación y evaluación de impacto ambiental en el caso de estudio del barrio Unir II en el tercio medio del humedal Jaboque, con el fin de determinar e identificar cuáles son las falencias u omisiones en el documento.
A partir de la realización de éste trabajo se logran identificar las falencias y omisiones con el fin de brindar la propuesta de mejora para cada una. Además, se plantea una nueva alternativa de evaluación de impactos por medio de los tensores y SE, para mejorar la determinación y evaluación apropiada de un ecosistema de gran importancia y poca atención.
Por último, se realiza el planteamiento de proyectos o actividades para ser incluidas dentro del PMA teniendo como propósito mejorar las condiciones actuales del humedal, enriqueciendo el documento y dándole mayor importancia al ecosistema.
Los mayores hallazgos están en relación a que el PMA aprobado del Humedal Jaboque está desactualizado y las autoridades competentes no se percataron de este hecho previamente, presentándose una desinformación entre las instituciones involucradas. También se encontró que no todas las actividades han sido llevadas a su etapa de ejecución, y por lo tanto la pertinencia de la propuesta de mejora que aquí se plantea se hace evidente, logrando diseñar las actividades específicas, junto con los objetivos, cronograma y tiempos de ejecución para que sean desarrollados en fases posteriores a este trabajo de grado. Jaboque wetland is located in Engativá, the tenth locality of Bogotá City, Colombia.
Recently the Environmental Management Plan (EMP) of Jaboque’s wetland was approved with
the main goal of preserving the ecosystem and improving its conditions. This EMP was done
with studies between 1998 and 2006 for ADESSA organization hired by the EAAB, being 2006
the year of the delivery version of the document.
Despite the fact that the EMP was approved just until 2015, the document did not present
major changes in comparison with 2006 version, so the good characteristics and also the mistakes
of the document by that time remained in the currently approved text. Based on that EMP, this
work started and was developed. This thesis aims for evaluating the environmental impact on the
case of Unir II neighborhood in the middle third of the Jaboque’s wetland, in order to determinate
and identify shortcomings and omissions of the document and the way to evaluate their impacts
on the ecosystem.
Based on the results of this work, it was possible to identify the key shortcomings and
omissions in order to propose the improvements for each one. Additionally, it is presented a new
alternative for impacts evaluation using tensioners and Ecosystem Services, to improve the
determination and appropriate evaluation of this important ecosystem that has had a secondary
role for long time for the authorities.
As a result, different projects and/or activities are proposed to be included in the
Environmental Management Plan, aiming the improvement of current wetland conditions, and
giving greater importance to the ecosystem.
In summary, the biggest finds are related to an outdated EMP approved for Jaboque´s
Wetland and that the competent authorities were not aware of it, presenting misinformation
among the institutions involved. It was also found that not all activities have been carry to their
implementation phase, and therefore the relevance of this work is evident, achieving design
specific activities, with the objectives, timetable and execution times to be developed in
subsequent phases of this dissertation. Jaboque wetland is located in Engativá, the tenth locality of Bogotá City, Colombia.
Recently the Environmental Management Plan (EMP) of Jaboque’s wetland was approved with
the main goal of preserving the ecosystem and improving its conditions. This EMP was done
with studies between 1998 and 2006 for ADESSA organization hired by the EAAB, being 2006
the year of the delivery version of the document.
Despite the fact that the EMP was approved just until 2015, the document did not present
major changes in comparison with 2006 version, so the good characteristics and also the mistakes
of the document by that time remained in the currently approved text. Based on that EMP, this
work started and was developed. This thesis aims for evaluating the environmental impact on the
case of Unir II neighborhood in the middle third of the Jaboque’s wetland, in order to determinate
and identify shortcomings and omissions of the document and the way to evaluate their impacts
on the ecosystem.
Based on the results of this work, it was possible to identify the key shortcomings and
omissions in order to propose the improvements for each one. Additionally, it is presented a new
alternative for impacts evaluation using tensioners and Ecosystem Services, to improve the
determination and appropriate evaluation of this important ecosystem that has had a secondary
role for long time for the authorities.
As a result, different projects and/or activities are proposed to be included in the
Environmental Management Plan, aiming the improvement of current wetland conditions, and
giving greater importance to the ecosystem.
In summary, the biggest finds are related to an outdated EMP approved for Jaboque´s
Wetland and that the competent authorities were not aware of it, presenting misinformation
among the institutions involved. It was also found that not all activities have been carry to their
implementation phase, and therefore the relevance of this work is evident, achieving design
specific activities, with the objectives, timetable and execution times to be developed in
subsequent phases of this dissertation.
Collections
- Administración Ambiental [227]
Related items
Showing items related by title, author, creator and subject.
-
Estrategia de educación ambiental para la preservación del sendero ecológico del Puerto fluvial de Guataquí Cundinamarca.
Urquijo Ramírez, Gina Lizeth (2023-03-17)El presente documento presenta la caracterización desde la dimensión ambiental del área del proyecto, así como, la ubicación georreferenciada del área que corresponde al sendero ecológico, y, por último, presenta una ... -
Formulación de un sistema de gestión ambiental conforme a la ISO 14001:2004 para la EDS Combustibles Mogue
Bustos Parra, Lina Johana (Universidad Piloto de Colombia, 2013-01-31)Este proyecto tiene como objeto aplicar los requisitos necesarios para implementar un buen sistema de Gestión Ambiental aplicados a las Estaciones de Servicio – E.D.S -, tomando como referencia la Norma internacional ISO ... -
Formulación e integración del sistema de gestión ambiental al SGC para la empresa Tecnoclean enfocados en las normas 14001:2004 y 9001:2008
León del Río, Diego Ernesto; Maldonado Suárez, Jonathan (Universidad Piloto de Colombia, 2013-01-31)En este trabajo de grado se formula un Sistema de Gestión Ambiental y su integración con el Sistema de Gestión de Calidad existente. Se requirió elaborar una revisión ambiental inicial el cual permitió determinar el estado ...